WORK METHOD STATEMENT FOR LIFT HOLE/TRENCH/PIT EXCAVATION WORK



  1. Prior to the excavation work setting out for the Lift hole/Pit shall be established. The setting out shall include the plan dimension and invert level as shown on the approved construction drawing.
  2. Upon completion of the setting out, Approval Chit/Request for inspection shall be submitted to the superintending Officer (S.O) or his/her representative (S.O.R) to enable them to do the inspection and verification on the setting out. No excavation work shall commence without any official instruction from S.O/S.O.R.
  3. Excavation work shall only commence upon acceptance of the setting out was done according to the construction drawings by the S.O/S.O.R.
  4. To avoid any unwanted incidents, Safety sign such as “Awas” and Safety tape shall be install where necessary.
  5. There shall be no excavation work been carried out during raining days.
  6. Anytime, during the excavation of the Lift trench/hole/pit, any machine/plant or equipment shall not be place at the edge of the trench/hole/pit. This is to prevent the vertical earth-wall from collapse and cause injury to the worker.
  7. As soon as possible, after the completion of excavation work, timber prop shall be erected to prevent the collapse of the vertical earth-wall before permanent concrete wall is constructed.
  8. All excavated earth shall be transported out to contractor dump site or Stock pile at the approved location within the site for later use. 


Proposed Machine/plant/equipment: 
  1. Excavator/Backhoe
  2. Dump truck/tipper truck
  3. Water pump.